Alvarado Water Treatment Plant

Alvarado Water Treatment Plant, San Diego, CA, USA

In March 2007, the second phase of the Alvarado water treatment plant’s major upgrade and expansion project closed with a formal ribbon cutting ceremony to unveil the facility’s new flocculation and sedimentation basins. Delivered in six phases over a period of 20 years, the scheme is intended to provide a state-of-the-art water treatment facility, with an expected useful life of 75 years and able to meet the anticipated needs of San Diego’s growing population until 2030.

"The Alvarado plant is the oldest of the three facilities responsible for supplying San Diego City."

Work on phase II first began back in March 2004, the newly completed cleaning basins having increased plant capacity from 570,000m³/day to 756,000m³.

The full cost of this part of the project was $54m. Previous phases cost just under $110m (Phase I) and $33m (Phase IA), with the overall cost of the remaining future stages (Phases III–V) being estimated at around $110m – principally financed by bonds and State funds.

BACKGROUND

The Alvarado plant is the oldest of the three facilities responsible for supplying San Diego City, having been first brought into service in 1951. San Diego County Water Authority began to modernise the plant back in 1993, completing two new 80,000m³ drinking water storage tanks in 1997. The following year, the work received the American Society of Civil Engineers’ National Award and the American Public Works Association Project of the Year.

However, despite this success, changes in federal and state drinking water regulations coupled with the compliance order issued by the California Department of Health Services in 1997 made further upgrades essential. In November 1998, Phase I of the project began.

WORK TO DATE

Completed in 2003, Phase I was a major construction programme aimed at enhancing the chemical treatment facilities and pumping arrangements.

This involved providing a number of new elements including a raw water blending vault, head-works with an associated rapid mix structure and eight filters. The eight pre-existing filters also underwent a series of upgrades, including the addition of filter-to-waste piping. Molecular chlorination disinfection facilities were installed, together with the construction of day tanks, bulk tanks and dosing facilities for both liquid polymer and ferric chloride.

In addition, facilities were constructed for dry polymer and potassium permanganate storage and dosing, while two pre-existing aqua ammonia tanks were relocated as part of the new provisions made for the finished water chemical treatment. New tanks and dosing facilities for sodium hydroxide were also built.

Other components of Phase I were the construction of a 4,300m³ wash-water supply tank, together with the buildings for effluent control, switchgear and the emergency generator. The Lake Murray raw water pump station required a complete tear-down and re-build, while the one at College Ranch underwent a programme of rehabilitation. The existing operations building was also upgraded and improved.

The demolition of the ageing and seismically unsafe Earl Thomas reservoir in 2002 marked the start of Phase IA. Stability in a region prone to earth movement was a key consideration in the design of its replacement and the effects of vertical, horizontal and overturning movements were important factors in selecting the new pre-stressed concrete tank.

Neoprene pads separate the roof and floor from the core-wall, which permits each to move independently in the event of an earthquake. Special cables have been used to control lateral seismic forces while allowing free movement of the wall under normal conditions. The new Earl Thomas tank measures some 124m in diameter and 11.5m deep, making it the largest of its kind in the world.

In addition to the tank itself, nearly 300m of tunnel was also constructed to accommodate the 1.5m diameter pipe which links it with the existing two 80,000m³ reservoirs. Connections were made to the phase I filters, via the effluent control also constructed in phase I.

Other work in this phase included improvements to the treatment plant entrance and site security, together with a car park and other amenities for visitors to Lake Murray. Phase IA was completed at the end of 2005.

Phase II ran from April 2004 to March 2007, when the ribbon was cut on the new flocculation and sedimentation basins, built along the south-eastern shore of Lake Murray. In addition to these basins, the electrical and control systems of the plant’s eight original filters were also upgraded as part of this element of the project. Work on the SD-17 pump station overlaps Phase II, running from July 2005 until its scheduled completion in June 2009.

REMAINING PHASES

"Further work is expected at the plant after the completion of the main project in 2013, including the possible construction of sludge processing facilities and eight new filters."

Phase III is scheduled to begin in the summer of 2010 and will involve the rehabilitation of the plant’s existing flocculation and sedimentation basins – work which is anticipated to take a year to complete.

Phase IV will provide major ozone treatment facilities, including the installation of contactors, ozone generators and allied treatment equipment, together with the construction of a separate operations building. This element of the project is expected to get underway in the winter of 2008 and scheduled for completion in summer 2010.

The final phase of the project is principally a finishing stage, including shoreline landscaping, post-construction provisions for storm-water, final site improvements and the construction of a back-up ozone generator and pump. Phase V is scheduled to begin in the summer of 2012 and be completed by the end of the following year.

Further work is expected at the plant after the completion of the main project in 2013, including the possible construction of sludge processing facilities and eight new filters, but no formal decision has been reached, nor timeframe suggested as yet.

KEY PLAYERS

The plant is owned by San Diego County Water Authority. Design work was done by Malcolm Pirnie and Richard Brady Associates, with construction management by CH2M Hill and Parsons acting as programme manager.

Nielsen Dillingham Builders was the main Phase I contractor with Helix Electric, J.R. Concrete, Pacific Coast Steel, Murphy Coatings and Watkins acting as major subcontractors. C.E. Wylie is the prime contractor for Phase IA and DYK is the tank subcontractor. Other subcontractors included The Tunnel Group, Hurricane Fencing, American Standard Concrete Pumping and A.O.

Reed. Ameron, Northwest Pipe, and American Pipe were the manufacturers and suppliers of the cement mortar lined and coated steel piping. Pratt Valve has supplied the valves and EIM the valve actuators. Victaulic has supplied pipe couplings, Tankentics provided chemical tanks and the pump supplier was Fairbanks Morse. The chlorination system and associated safety equipment was supplied by US Filter. Archer Western was the general contractor for Phase II.

Printable Version Click here for printable version



Expand Image
San Diego's oldest existing water treatment plant, Alvarado, has received a National Historic Award from the American Water Works Association for its contributions to water supply and technological development.
San Diego's oldest existing water treatment plant, Alvarado, has received a National Historic Award from the American Water Works Association for its contributions to water supply and technological development.
Expand Image
Phase II ended with the formal ribbon cutting to unveil the new basins. San Diego Mayor, Jerry Sanders, and Council member Jim Madaffer joined the City of San Diego Water Department staff at the ceremony.
Phase II ended with the formal ribbon cutting to unveil the new basins. San Diego Mayor, Jerry Sanders, and Council member Jim Madaffer joined the City of San Diego Water Department staff at the ceremony.
Expand Image
Aerial view of Lake Murray; the recently completed flocculation and sedimentation basins were built along the south-eastern shore.
Aerial view of Lake Murray; the recently completed flocculation and sedimentation basins were built along the south-eastern shore.
Expand Image
DYK completing the vertical pre-stressing and the exterior finish of the new Earl Thomas Reservoir. The location called for good seismic stability and several features have been incorporated into the design to mitigate the potential effects of tremors.
DYK completing the vertical pre-stressing and the exterior finish of the new Earl Thomas Reservoir. The location called for good seismic stability and several features have been incorporated into the design to mitigate the potential effects of tremors.
Expand Image
Aerial view of the site during Phase 1A of the work.  The programme of renovation and construction began in 1993 and will be completed in 2010 or later, depending on bond financing and State grants.
Aerial view of the site during Phase 1A of the work. The programme of renovation and construction began in 1993 and will be completed in 2010 or later, depending on bond financing and State grants.
Expand Image
The new Earl Thomas reservoir was dedicated in December 2005. The San Diego Mayor, councillors, community members, contractors and city staff attended the event, which also unveiled the new parking lot for Lake Murray visitors.
The new Earl Thomas reservoir was dedicated in December 2005. The San Diego Mayor, councillors, community members, contractors and city staff attended the event, which also unveiled the new parking lot for Lake Murray visitors.
Expand Image
Aerial view during Phase 1 construction; the Lake Murray raw water pump station underwent a complete re-build.
Aerial view during Phase 1 construction; the Lake Murray raw water pump station underwent a complete re-build.


client logon
Home
Products & Services
Company A-Z
White Papers
Jobs & Careers
Press Releases
Advertise With Us
Events & Exhibitions
Newsletter
New On This Site
About Us
Atom FeedRSS Feed
What is RSS?