Czajka Wastewater Treatment Works, Poland

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Population equivalence served
2.1m (on completion)
Capacity
Current
200,000m³/day
Final
435,000m³/day (normal); 515,000m³/day (peak)
Sub-Vistula flow rate
3-11 m³/sec (to include additional rainwater element)
Sludge production
Current
80,000tpa

By the end of 2010, when the project to upgrade and expand Warsaw’s Czajka WWTP has been completed, the city’s first wastewater treatment works will be Poland's largest.

Designed around a population equivalence of 2.1m, the project will more than double the plant’s present 200,000m³/day inflow to routinely deal with a daily 435,000m³, rising to a potential 515,000m³/day at peak times. As a result, sludge production will double to 160,000 tons per annum, calling for a new thermal treatment process to be installed at the plant to reduce the volume produced to facilitate disposal.

The work also includes extensive associated earthworks, civil engineering, automation and electrical elements and will be undertaken in two phases to enable the plant to remain operational throughout.

The project cost is €500m, with funding from the EU cohesion fund and the local municipality.

Czajka WWTP background

"The project will more than double the Czajka plant’s 200,000m³/day inflow."

Situated in 56 hectares of the Bialolęka borough in northeast Warsaw, Czajka WWTP was completed in 1991, after a building programme that took 17 years to come to a close. The lengthy construction meant that much of the technology and equipment was outdated by the time the plant came online, forcing the almost immediate start of a series of modernisations.

Although the works relied on relatively old mechanical and biological systems to produce the necessary BOD and suspended solids removal, it managed to produce respectable quality effluent by the standards of the time and represented a big advance on the previous arrangements – the discharge of untreated wastewater into the Vistula.

The main driver on the extensive modernisation project was the need to meet EU wastewater standards – including limits on nitrogen of 10mg/l and 1mg/l for phosphorus, effective from January 2007 – and to provide adequate treatment for all urban effluent flows.

Czajka programme of works

The Czajka upgrade and extension project forms part of the Warsaw water supply and wastewater treatment scheme, which consists of three phases. Phase 1 involved the construction of new sewers and collectors for the city’s new Poludnie WWTP, funded by an EU grant awarded in 2001.

Phase 2 extended and improved aspects of the city’s potable water supply, including upgrading the treatment process at the Zaklad Wodociągu Centralnego and Zaklad Wodociągu Pólnocnego plants, the construction of a new water distribution network and implementing modern computer control for both the water supply and wastewater systems.

The Czajka project – comprising the plant upgrade, the construction of a thermal drying facility for the sludge, new transmission sewers and the modernisation of the wastewater system in Bialolęka, Mlociny, Bielany and Rembertów – stands as the largest element of Phase 3.

To date, the plant has been responsible for processing sewage only from right-bank Warsaw and Legionowo, the flow from areas on the left bank of the city being discharged directly into the Vistula at a rate of more than 300,000m³ /day. By the end of the programme of work, Czajka will also accept and treat this wastewater, which will be transported to the plant beneath the river.

This will have obvious benefits to water quality in the Vistula, improve the environment of communities south of the city and ultimately reduce the contaminant loadings entering the Baltic Sea.

Czajka plant improvements

One of the most significant plant improvements centres on sludge management. The plant’s existing disposal arrangements rely on land-spread, which is no longer an acceptable route.

"One of the most significant plant improvements at Czajka centres on sludge management."

To reduce the volume of material and facilitate its landfilling, the project includes the provision of a new thermal sludge treatment and ash condensation facility, with an average output of about 24 tons of sludge an hour.

A second key aspect of the facility’s modernisation programme involves a completely new automation installation, providing a comprehensive visualization, control and monitoring system. The design includes nine process stations, more than 60 controllers, two redundant servers, five operators’ workstations, more than 1,000 analogue measurements and in excess of 2,000 drives.

Once installed, the SCADA automation and monitoring will ensure optimal flow through the plant processes, providing full control and operational visualisation, with real-time data measurement, equipment status, alarm notification and system failure alerts.

Treatment at the plant is also to be upgraded to meet required EU standards using a range of technologies developed by OTV and Kruger, including the implementation of a chemical scrubbing system to reduce any perceived odour nuisance.

The Czajka project's key players

The client is the Miejskie Przedsiębiorstwo Wodociągów i Kanalizacji w Warszawie (Warsaw Water and Wastewater Company). The consortium responsible for project delivery comprises Veolia, Warbud, OTV, Kruger and WTE Wassertechnik, with plant automation being provided by Siemens.

EnviroSim conducted the calibration study to characterise the wastewater and establish the nitrification rate as well as developing pre-design options for the project and the sludge treatment design studies were carried out by WS Atkins-Polska. The project is funded by the EU and from local funds.

Regulatory oversight at the national level is the responsibility of the National Fund for Environmental Protection and Water Management, together with the Ministries of Environment and Regional Development.



Expand Image Expand Image
View over the River Vistula. The population of Warsaw is growing fast, and the Czajka WWTP will protect water quality and allow the plant to meet the demands of EU discharge standards.



Expand Image Expand Image
The Czajka WWTP will benefit from extensive upgrades, including big improvements to automation and process control.



Expand Image Expand Image
The Czajka WWTP was opened in 1991, after a building programme that took 17 years to complete. The current upgrade and extension will equip it to meet the city’s projected future needs.



Expand Image Expand Image
The view from the Świtokrzyski Bridge over the Vistula towards the Old City. The project will ensure that sewage from both banks of the river is treated for the first time in Warsaw’s history.



Expand Image Expand Image
The existing plant relies on relatively old mechanical and biological systems to treat the inflow before discharge.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the water and wastewater industry