Bray Wastewater Treatment Works, Ireland, Ireland




Key Data


Shanganagh Bray wastewater treatment infrastructure works are being carried out in Shankill, Dun Laoghaire County, Ireland, by Dun Laoghaire-Rathdown County Council in association with Wicklow County Council and Bray Town Council.

The project involves construction of a wastewater treatment plant, renovation of the existing Bray Pumping Station and construction of a 6km transfer pipeline from Bray to Shanganagh.

The mechanical, electrical, instrumentation, controls, automation (MEICA) works associated with the Bray Stormwater Storage Tank were also refurbished.

The €65m project was started in November 2008 and the plant was completed in July 2010. Construction of the Transfer Pipeline started in 2011 and is expected to be completed in 2012.

The new plant, constructed at the site of the existing Shanganagh wastewater treatment works, is capable of treating 43,700m³ of wastewater a day. It was commissioned in July 2011 and is expected to be fully operational by 2012. The facility is estimated to serve a population of 186,000 people.

Purpose of Bray wastewater treatment project in Dun Laoghaire County, Ireland

"Shanganagh Bray wastewater treatment infrastructure works are being carried out in Shankill, Dun Laoghaire County, Ireland."

The project is part of a broader programme called the Water Services Investment Programme. The €5bn investment programme is committed to elevate utility infrastructure for water and drainage throughout the county.

The main purpose of the project is to upgrade the existing facility in accordance with the Urban Wastewater Treatment Directive and associated Irish Regulations.

The upgraded facility also complies with other EU directives and National Regulations meant for environment protection.

The project was also undertaken to achieve full secondary treatment of the wastewater generated by the Shanganagh and Bray areas.

Discharge of the untreated wastewater into Dublin Bay was also stopped with the completion of the project.

It is expected that Dun Laoghaire Rathdown and Bray areas will gain social, economic and environmental benefits from the project.

Bray wastewater treatment project background

In 1998, MC O'Sullivan Consulting Engineers was commissioned to prepare a Preliminary Report involving the upgradation of collection system, wastewater treatment and sludge disposal arrangements.

The contract also required the preparation of an Environmental Impact Statement (EIS) for the new wastewater treatment plant at the existing site of the Shanganagh wastewater treatment works.

The EIS was approved in October 2001. The traffic management plan for the construction of the project was approved by the Traffic Section of Dun Laoghaire-Rathdown County Council in November 2008.

Contract Number 1, meant to upgrade the existing waste water treatment works plant at Shanganagh, was sanctioned by the Department of the Environment, Heritage and Local Government in July 2008. Contract Number 2, which involves construction of the transfer pipeline from Bray to Shanganagh and a stormwater storage tank at Old Bray Golf Club, was approved in April 2010.

Wastewater treatment plant design features

The raw sewage lifting pumping system has a total of seven pumps, three of which are rated 55kW and the remaining rated at 200kW. Frequency shifters are fitted in the three 55kW pumps and one of the 200kW pumps. At any given time, six pumps may be operational, with one 200kW pump kept as reserve.

The plant is provided with four 1m-wide channels for the purpose of screening. Sand and grease are removed from the screened water by using four sand and grease removal lines.

Each line has a length of 25m and width of 6m. The excess of wastewater flow is transferred to a 1,300m³ storm tank, which is cut from the inlet chamber by an automatic penstock. When the inlet chamber gets empty, the penstock automatically opens up to divert the wastewater to the process.

The plant's biological reactor consists of four streams, each divided into 600m³ capacity anaerobic and 3,000m³ capacity aerobic zones. The entire plant is covered for odour control. An odour treatment system is also installed at every stage of the treatment process to filter the odours.

New additional air treatment units are being installed to eliminate the flaws found during plant commissioning. It will be completed in 2012.

Treatment of domestic and industrial wastewater and contractors involved

Domestic as well as industrial wastewater arrives at the facility for treatment through a network of gravity pipelines and pumping stations.

"The project is part of a broader programme called the Water Services Investment Programme."

In the pre-treatment process, the incoming wastewater is screened to remove rags and gravel. The resultant wastewater is then passed to the primary sedimentation tanks for the removal of larger solids.

After settling down, these solids are removed from the primary sedimentation tanks for sludge treatment process.

After primary sedimentation, the wastewater is biologically treated by adding air to the secondary treatment tanks. Lastly, the biologically treated wastewater is sent for final clarification. The treated wastewater is finally discharged to Killiney Bay.

The project (excluding transfer pipeline) was carried out by the SDD Shanganagh consortium, which is constituted of Sisk, Dragados and Drace. The consortium is also responsible for operating and maintaining the plant and associated facilities for 20 years.

Kildownet was contracted to construct all the major structural elements of the facility. Marshall Day Acoustics was contracted to predict the noise emissions from the construction site.

Roadbridge was awarded €3.9m contract in July 2011 for construction of the Transfer Pipeline and associated works. McCarthy Hyder Consulting Engineers is the consultant designer. PSCS is the road works contractor.

Discharge of untreated wastewater into the Dublin Bay will also be stopped with completion.
The Bray Wastewater Treatment Works serve the fourth largest town in Ireland.
Schematic showing conventional activate sludge process and membrane bioreactor process.