Brightwater Project, United States of America




Key Data


Construction of the new Brightwater WWTP, which began with preliminary demolition and clearance work on the 114 acre site in November 2005, was originally scheduled to enter service in 2010.

Delays in construction work, however, postponed the plant opening to September 2011. The facility will have an initial peak flow capacity of 495,000m³/day, rising to a daily 645,000m³ by 2040. It serves about 189,000 people in north King and south Snohomish counties.

Conveyance pipeline system

In addition to the new plant itself, the project requires the construction of a major conveyance pipeline system, together with a new marine outfall which discharges the treated effluent directly into Puget Sound. Construction of the 600ft deep outfall began in spring 2008 and was completed during the same year.

"Cost of the MBR was expected to reach $30m, with a further $50m allocated for state-of-the-art odour control measures."

A major portion of the conveyance pipeline system is the Brightwater Tunnel (BT). The 13-mile tunnel was built in four sections, BT-1, BT-2, BT-3 and BT-4. The excavation work on BT-1 or the East Tunnel began in September 2007 and was completed in November 2008.

Works on BT-2 were launched in September 2007. The Tunnel boring machine (TBM) for BT-3 was launched in March 2008 by Vinci, Parsons and Frontier-Kemper (VPFK). The TBM for BT-4 was launched in September 2008. The four-mile eastbound BT-4 tunnel was completed in June 2009.

Construction on the four-mile BT-3 tunnel, the final segment of the conveyance pipeline system, resumed in October 2010 after works terminating in June 2009 due to a severe damage to the TBM. Jay Dee Contractors and Frank Coluccio Construction (JDC) joint venture, which completed the BT-4, was hired to drill the remaining 1.9 mile section of BT-3 tunnel. It was completed in August 2011.

The Brightwater Tunnel is expected to enter service in September 2012. Complete pipe installation, including the conveyance system, is scheduled for 2012. Once connected to the conveyance system, the plant's average daily flow will be about 90,850m3.

Brightwater Tunnel project background

The population of the Puget Sound region has more than doubled in the last 40 years and projections of the continued growth indicated that by 2010 the King County wastewater treatment system would have insufficient capacity.

In November 1999, the Regional Wastewater Services Plan was approved and the process of identifying and evaluating potential sites, marine outfall zones and construction methods for a new plant began the following year.

This ultimately led in December 2003 to the selection of a site for the planned facility - known as the Route 9 site - near the city of Woodinville, with an associated conveyance pipeline along the border of King and Snohomish counties and an outfall off Point Wells.

With adequate wastewater treatment widely seen as one of the key factors in regional sustainable economic development, in 2004, the Puget Sound Regional Council placed Brightwater on its top ten list of priority projects.

After a comprehensive series of environmental impact assessments and an extensive programme of public consultation, this site selection was formally reaffirmed in July 2005 and preliminary work began four months later.

Membrane bioreactor (MBR) plant

Preliminary treatment of the influent is conventional, using mechanically cleaned screens and grit removal, with both processes being covered and vented to minimise odour.

The primary treatment approach, which treats most of the inflow into the plant, also has a traditional design and consists of covered rectangular clarifier units, vented through an odour control system.

The secondary treatment process, however, employs MBR technology as an alternative to the more conventional activated sludge method. This approach comprises 2mm fine screens to exclude any remaining debris and inorganic material, bioreactor aeration basins and, finally, the membrane tanks where the last stage ultra-filtration takes place.

The facility has a design potential which allows for up to 220 membrane cassettes, providing a final average daily capacity of 205,000m³ by the year 2040.

The GE's ZeeWeed MBR technology selected consists of a suspended growth biological reactor integrated with an ultra-filtration membrane system and provides substantially better final effluent quality than conventional secondary treatment. The membranes are immersed within the aeration tank and bathed in the mixed liquor.

A pump then draws water through the ultra-filtration membranes, while periodic intermittent airflow introduced at the bottom of the module cleans the surface of the membrane fibres.

"Preliminary treatment of the influent is conventional, using mechanically cleaned screens and grit removal."

This approach effectively overcomes the poor sludge settling, often characteristic of conventional activated sludge processes and allows for significantly higher mixed liquor solids concentrations - typically in the range of 8,000mg/l to 10,000mg/l. The elevated biomass concentrations supported result in the highly effective removal of both soluble and particulate biodegradable material.

The combination of high quality effluent and the system's operational reliability were major drivers in the decision to adopt this technology.

At times of particularly high flows, provision will be made to split the influent after the preliminary stage, with the excess undergoing an enhanced primary treatment before being recombined with the effluent from the MBR for disinfection with sodium hypochlorite and discharge to Puget Sound.

Odour control criteria

Stringent criteria have been established to ensure effective odour control, with King County having committed to a goal of no odours detectable beyond the site boundary. To achieve this, all process units are covered and the air collected is routed through the odour control system.

This comprises multistage chemical scrubbers, with a final carbon adsorption stage, which will also be used to treat any digester gases discharged through pressure release vents.

MBR plant output

Of the four classes of reclaimed water identified by Washington state, Class A - which may be used for non-potable industrial processes and irrigation - is the most stringent. The plant will initially offer a 20,000m³/d Class A water reclamation facility, with space reserved on-site for future expansion to a final daily production of 643,520m³.

King County has been successfully recycling biosolids for more than a quarter of a century, using it for applications in agriculture, forestry, landscaping and gardening. Biosolids from the new plant undergo thickening, anaerobic digestion and dewatering processes on-site before being removed for beneficial off-site use in these established outlets.

Storm water management

As befits a major moder construction site, environmental concerns have been given great consideration - the innovative approach to storm water management being a case in point. Rainwater running across the bare soil of construction sites can quickly pick up a variety of particles and pollutants, which inevitably then end up in local waterways, eroding the soil and increasing turbidity in the receiving waters. In an attempt to avoid this, silt fences, sediment traps and check dams are often used.

Chemical treatments are also employed where building work sits alongside particularly sensitive watercourses, or when construction coincides with high seasonal rainfall; a situation which can create unique issues for storm water management. Such chemical treatment - though effective - is expensive.

To avoid this costly route and maximise both environmental and economic gains, the Brightwater site made use of forest filtration - allowing the site's large undisturbed areas of trees and vegetation to treat the water runoff.

Storm water run-off from the southern end of the site where most of the building work took place was pumped to an installed sprayer system, which irrigates the forestry north of the site minimising the use of chemicals while still meeting the appropriate standards. Ground filtration itself is not a new idea, but it is not usually used on construction sites and seldom at this scale.

Cost of the Brightwater project

The cost of the MBR was initially expected to reach $30m, with a further $50m allocated for state-of-the-art odour control measures; the total construction cost was estimated at $280m, with an additional $88m ear-marked for landscaping and mitigation. The final cost, however, was $1.8bn due to delays and inflation.

Key players involved in the project

King County's Wastewater Treatment Division is the client. Hoffman Construction was the general contractor and construction manager.

"Delays in construction work, however, postponed the plant opening to September 2011."

Hoffman was responsible for the liquids processing facilities, and overall site and civil constructions. The membrane system for secondary treatment was supplied by GE Water & Process Technologies.

The Brightwater treatment plant's engineering and architectural services were provided by the engineering consulting company CH2M Hill. CH2M Hill also provided the project siting, construction support and environmental services for the plant.

The company teamed up with subconsultants including Brown and Caldwell and Mithun Architects + Designers + Planners for the Brightwater plant's design. The solids stream and odour control systems were provided by Kiewit-Pacific under a design-bid-build contract.

A series of impressions of the new plant; finished facility model (centre); artist's impression of the new public open space areas (top left); example of onsite building design (top right); artist's impression of the new wetland habitats (bottom left); the planned education building (bottom right).
Schematic of the new conveyance system which, together with a new marine outfall and the plant itself, completes the project's programme of works.
Project schematic. Wastewater treatment capacity has been identified as one of the key factors in the region's future economic development.
Map of King County service area. The population of the Puget Sound region has more than doubled since 1960.
Annotated composite aerial view of the plant. Construction work on the 114-acre site, which began in November 2005, continues on schedule for its planned entry into service in 2010/11.
Main picture, a typical section through the new outfall; a tug pulls outfall sections into place (top left); a section of the diffuser (top right); near-shore trench sheeting (bottom left); graphic of barge-mounted cranes lowering outfall segment (bottom right).