Cholla Water Treatment Plant, AZ, USA

 

Key Data:

Plant rated capacity
114,000m³/day
Actual peak capacity (2002-3)
106,000m³/day
Micro-filtration demonstration capacity
1,900m³/day
Upgrade budget
$7 million

Project Timeline:

Plant opened
1980
Micro-filtration demonstration project
2000
Granular activated carbon filter pilot
2002
Solids handling facility constructed
2002-3

Key Players:

Client
City of Glendale
Micro-filtration contractor
Malcolm Pirnie
Power system upgrade
DL Engineering & Controls
SCADA and control room upgrades
Jensen Systems
Other contractors
DDH Consulting, HDR Engineering