Key Data:
Dry weather flow
33,000m³/day
Wet weather flow
62,000m³/day
Dry weather flow
35,000m³/day
Wet weather flow
151,500m³/day
Onsite storage capacity
700,000m³
Project Timeline:
Phase 1 began
20th October 2006
Phase 1 scheduled for completion
October 2007
Phase 2
June 2007–December 2007
Phase 3
July 2007–June 2009
Phase 4
June 2008–February 2009
Phase 5
July 2009–April 2010
Phase 6
June 2008–January 2010
Phase 7
July 2009–July 2011
Phase 8
October 2010–April 2012
Key Players:
Plant owners
Redding Wastewater Utility
Construction management / engineering
CH2Hill
Construction
TICO Construction
Project funding
City wastewater revenues and California Water Resources Control Board’s Revolving Fund.