|
On 23 April 2002, the Board of Lee County Commissioners approved a series of plans for water and wastewater facilities, qualifying the county for low-interest state loans to help fund the work. The construction management contract for the expansion of the existing Corkscrew Water Treatment Plant from 38,000m³/day to 57,000m³/day was awarded to Earth Tech on 8 July 2003. This is one of two separate but integrated projects Earth Tech are undertaking in the county, the allied contract being to build a new storage facility and pump station at the Green Meadows WTP, together with an interconnection between this facility and the Corkscrew plant. The $13 million project is principally intended to improve the county's water supply capacity and provide the system with greater operational flexibility. This principally involves the construction of lime softening, aeration and re-carbonisation facilities together with new filtration system, storage tanks and control buildings. The work also includes associated control systems, pipe-work and various site improvements such as clearing, paving, fencing and landscaping. Johnson Engineering were appointed to provide professional engineering and related services for the expansion of the Corkscrew plant on 18 November 2003 and work started shortly afterwards. Their contract for preliminaries included the test wells, surveying and geo-technical investigations, easement acquisition and the project's initial and final design phases. During the construction phase, they will provide engineering support and oversee the plant permitting process. Completion is scheduled for 31 March 2005. CORKSCREW WATER PLANT BACKGROUNDLee County is experiencing rapid growth. In 1950, the population was 23,400; by 1970, it had grown to 105,200 and nearly doubled over the next ten years. By 2000 it had reached almost 450,000 and population estimates suggest that the county will have approximately 650,000 inhabitants in 2020. Much of this forecasted growth is expected as extensions of existing main population centres - the Cities of Fort Myers, Cape Coral, Sanibel and Bonita Springs and the Town of Fort Myers Beach; all except Fort Myers have been developed since 1970. Unsurprisingly, the size and speed of this anticipated growth are the main drivers of the expansion programme for the area's water supply. The county's current daily potable water supply capacity is around 102,000m³ with an average population density of 225 inhabitants per km². To meet the demands predicted for 2020, when the population will exceed 650/km², it is projected that this will have to increase by nearly 70% to 170,000m³/day. The present expansion of the Corkscrew plant, together with the allied Green Meadows project, forms an important part of the response. Other elements in the county's overall water strategy include increasing the Olga WTP to 38,000m³/day and expanding the wastewater treatment capacity at both the Gateway and Fiesta Village plants to 19,000m³/day apiece. CORKSCREW WATER PLANT DESIGNThe existing Corkscrew WTP has served Lee County well since it was first constructed, winning the Department of Environmental Protection's Award for Excellence in 1982 along with numerous safety awards over the years. Ground water drawn from the local sandstone aquifers via the nearby Corkscrew well fields forms the raw supply. On arrival at the plant, the water is first aerated to remove hydrogen sulphide, iron and manganese. Subsequently, lime is added to precipitate colloidal carbonate impurities and soften the water. The carbonate hardness produced alters the buffering capacity of the water, with carbon dioxide being added subsequently to stabilise and adjust the final pH. The water is then disinfected by dosing with chlorine and ammonia before passing through eight mixed-media (gravel / anthracite / sand) filters and entering the plant's storage tanks prior to distribution. Essentially the same treatment processes have been retained in the design of the expansion and improvement project. To enable the necessary 19,000m³/day increase in capacity, a new 16.5m-diameter lime softening contact tank will be constructed with an associated lime storage silo and dosing equipment. Other elements to be provided include four new Leopold filter units, a carbonisation basin, a series of high volume air blowers and piping, together with appropriate electrical control panels, instrumentation and control systems. Standby generator switchgear will also be installed and some minor interior remodelling undertaken. In addition, the interconnection between the Corkscrew plant and Green Meadows, where two 19,000m³ ground storage tanks, a high service pumping station and a new feed into the existing transmission mains are to be constructed, will give the system added operational flexibility. KEY PLAYERS The Corkscrew WTP is owned by Lee County and operated by their Utilities Division. The State of Florida provided low-interest loans. Earth Tech was the main contractor and acted as a member of design team to provide construction recommendations, schedules and reviews. During construction they are also responsible for project management and cost control. Johnson Engineering was responsible for the preliminary and design phases. They will provide engineering and related services during the construction phase of the expansion. |
![]() Expand ImageThe Corkscrew WTP won the Department of Environmental Protection's Award for Excellence in 1982 along with numerous safety awards over the years. The expansion will increase capacity from 38,000m³/day to 57,000m³/day. |
![]() Expand ImageProject preliminaries included an extensive programme of surveying and geo-technical investigations. | |
![]() Expand ImageSite preparation began in late 2003 and completion is expected for March 2005. | |
![]() Expand ImageIn addition to a new carbonisation basin, a 16.5m-diameter lime softening contact tank, chemical storage silo and four new Leopold filter units will also be constructed. | |
![]() Expand ImageLee County has seen rapid population growth since 1950, which is predicted to continue for at least ten years. The Corkscrew expansion, together with the allied Green Meadows project, form part of the response to this. | |
![]() Expand ImageThe expansion retains the same main treatment processes as the existing plant. | |
![]() Expand ImageThe project demands extensive pipe-work, including a major interconnection between the Corkscrew and Green Meadows WTPs and a new feed into the existing transmission mains. | |
![]() Expand ImageCareful timeline management ensures that components are pre-delivered to the site, minimising the risk of installation delays. |