|
When the major three-year upgrade of the E.L. Smith WTP ends in early 2008, capacity will have been almost doubled – yielding a 25% increase in potable water available to the Edmonton service area and ensuring that demand can be met for at least the next 15 years. Using a unique partnership approach to design and construction, in addition to safeguarding the continuity of future supply, the project will also bolster the response to seasonal challenges such as spring-run-off and periods of drought. The work at the plant involves upgrades to the treatment process and filters, the installation of a new disinfection system and a series of general site improvements. The overall project additionally includes the construction of a new river water intake, pump house and transmission line. "The project will also bolster the response to seasonal challenges such as spring-run-off and periods of drought."
Some temporary civil work is also required. To allow a water pipe to be installed, a portion of the North Saskatchewan River will have to be blocked off with sheet piling and, subsequently, a temporary bridge and enclosure structure erected to permit the new concrete intake to be constructed on the river bed. The project cost is CAN$140m. BACKGROUND Located by the North Saskatchewan River, some 11 miles (18km) upstream of Edmonton, the E. L. Smith WTP is one of the city’s two treatment plants. An earlier proposed upgrade to the facility, originally built in 1976, was deferred in 1991, as reduced summer peak demands, decreased commercial consumption and a re-evaluation of anticipated regional population growth had lessened the immediate need. In the following years, EPCOR – the plant’s owner/operators, responsible for the supply to the city itself and 45 outlying regional communities – undertook an extensive programme to encourage water conservation, improve quality and optimise the plant. While water consumption per customer has been very successfully reduced as a result and the optimisation work has enabled the plant to achieve 20% higher production than its original design specification, this has been largely offset by steady regional growth. With recent forecasts predicting that the population in the Edmonton Capital region will approach 1.1 million by 2009, upgrading the E. L. Smith works gained renewed impetus. THE PROJECT Despite increasing its capacity to 400 million litres/day, the project only calls for a minimal expansion of the plant footprint, with improvements and further optimisation to the treatment process playing a significant part in making this possible. Apart from the modifications to the filtration provision and other general improvements, the plant upgrade will see the replacement of the existing standard chlorine tonner disinfection system with a new facility producing sodium hypochlorite onsite. The UV disinfection system – said to be the largest in the world when it was installed in 2002 – will have additional capacity added with a 1200mm next generation UV disinfection reactor from Calgon Carbon. In addition, the wider project will require the installation of 155m long x 1600mm twin raw water lines connected to a 955 MLD intake structure, equipped with a unique fish return system to protect local fish stocks. An extension to the transmission main will also be installed to increase service to the rapidly expanding population in the south and south east, requiring the construction of a 560m-long transmission tunnel 10m under the North Saskatchewan River. Mitigating any potential environmental impacts from the work featured in the project planning from the outset. Alberta's North Saskatchewan River Basin, covering an area of some 28,000km² upstream of Edmonton, is an area of outstanding natural beauty and uniqueness. The source of the river – and thus of Edmonton’s drinking water – is the Saskatchewan Glacier in the Columbia Icefields, the only glacier in the world to drain into three oceans. The Athabasca River drains into the Arctic Ocean to the north, the Columbia River flows westward into the Pacific, while the North Saskatchewan River itself empties into the Atlantic to the east. In addition to the ongoing routine programmes of watershed monitoring and protection, EPCOR set out to ensure that all the work to be undertaken as part of the project was designed to minimise its effect on the watershed and surrounding environment. Construction was also planned so that the local communities would experience the least possible disruption. Several governmental regulatory agencies were involved in consultations to achieve these goals, with comprehensive sedimentation and erosion control plans being developed to minimise damage to the environment. Tunnelling work under the river has been assessed to have little impact on the local habitat. TREATMENT Treatment at the plant employs the conventional steps of coagulation, flocculation and filtration. Raw water is drawn from the deepest part of the river via intakes and passes through screens before entering the low lift pump station which directs water into the treatment plant. There alum, primary polymer and powdered activated carbon are added, on-line analysers allowing the dosage to be adjusted as required. After a high intensity rapid agitation to distribute these additions, the water is mixed more slowly to encourage floc formation within the clarifying basin. The flocculation/sedimentation phase detention period is between two and four hours. Subsequently, filter polymer – which helps improve particulate removal – and chlorine are added, the flow then passing to dual media gravity filters. UV sterilisation follows before the water is dosed with ammonia, fluoride and sodium hydroxide. "Mitigating any potential environmental impacts from the work featured in the project planning from the outset."
The ammonia combines with the chlorine to form monochloramine, which acts as a persistent disinfectant in the system. The fluoride brings the river water’s natural 0.15mg/l of fluoride up to the 0.8mg/l recommended by Health Canada; the sodium hydroxide is added to raise water pH to minimise corrosion and reduce the potential leaching of lead, iron and copper. Finished water flows into a holding reservoir, before finally entering the distribution system. KEY PLAYERS EPCOR is the plant owner/operator. Design assistance on the project was provided by Associated Engineering, with a range of general contractors including Clark Builders, Sureform, Lockerbie & Hole providing construction services. The City of Edmonton Drainage Branch is responsible for the tunnelling and water main installation. The major suppliers of equipment comprise Summit Valve for large diameter vales up to 2100mm, Northwest Pipe for raw water and transmission main piping, and Severn Trent for the sodium hypochlorite generator equipment. Calgon Carbon is providing the UV disinfection reactor. |
![]() Expand ImageArtist's impression of the finished plant. The city of Edmonton lies some 11 miles downstream; with a population predicted to exceed 1 million by 2009, upgrading the facility is intended to provide a 25% increase in the area’s available drinking water. |
![]() Expand ImageAlberta's North Saskatchewan River Basin covers 28,000km2 upstream of Edmonton and is a unique area of outstanding natural beauty. | |
![]() Expand ImageNew river intake diagram. The structure itself lies on the river bed, 3m below the surface. Given its low suction velocity, most fish have no difficulty in avoiding it; a novel mechanism gently returns small ones that slip through the screen downstream of the intake. | |
![]() Expand ImageLocation map of EPCOR facilities in the region. The two WTPs in Edmonton – Rossdale and E L Smith – have a current total capacity of 530 million litres per day. | |
![]() Expand ImageThe source of the North Saskatchewan River – from which Edmonton draws its drinking water – is the Saskatchewan Glacier in the Columbia Icefields, the only glacier in the world to drain into three oceans. | |
![]() Expand ImageCross section showing the transmission route. Nearly 600m of transmission tunnel is being constructed 10m below the North Saskatchewan River to serve the rapidly expanding population to the south and south east; one of the access shafts is over 60m deep. | |
![]() Expand ImageMap of the North Saskatchewan watershed. |