Key Data:
WTP Treatment Capacity
40,000m³/day
Pumping Station Rated Capacity
150,000m³/day
Aeration Tank Diameter
65m
Project Timeline:
Work Commenced
Summer 2005
Pumping Stations Completed
Summer 2007
System Operational
Summer 2008
Key Players:
Sponsor
Iraqi Ministry of Public Works
Oversight/Project Management
US Corps of Engineers - Gulf Region Division
Construction Management
Awaf Abdul Rahim
Construction
Local Iraqi contractors/workforce