Key Data:
Plant Type
Wastewater treatment & recycling facility
Plant Design
Three stage biological treatment, membrane filtration & reverse osmosis
Flow Type
Domestic and industrial wastewater
Type
Class A recycled water
Number of Membrane Modules
2592 (12x 216 modules)
Domestic Wastewater
8 cells
Industrial Wastewater
4 cells
Project Timeline:
Planning and Design Commenced
January 2006
Construction Date of Maryvale Facility
February 2007
Construction Date of Pipeline
August 2007
Completion Date
End of 2008
Gippsland Water Take Over Date
Late 2010
Key Players:
Principal Sponsor
Gippsland Water
Project Management
Transfield Services
Engineering Delivery Infrastructure
Parsons Brinckerhoff
Other Contractors
Boom Logistics, GBG Concreting, Morrow Plumbing, Nilsen, SM Urban.