GMR (Great Man-made River) Water Supply Project

Specifications - GMR (Great Man-made River) Water Supply Project, Libya


Key Data
Phase IProvide 2 million m³/day along 1,200km pipeline from As-Sarir and Tazerbo to the Ajdabiya reservoir to Benghazi and Sirt
Phase IIPumping from the south western aquifer (Fezzan) to Tripoli and Jeffara plain
 Designed for future expansion in Phase III
Phase IIIExpansion of existing Phase 1 system; additional 1.68 million m³/day (increasing total capacity to 3.68 million m³/day); 8 new pumping stations; 700km of new pipeline
 Supply 138,000m³/day to Tobruk and the coast; new wellfield at Al Jaghboub; reservoir south of Tobruk; 500km of new pipeline
Phase IVExtension of distribution network; construction of a pipeline linking the Ajdabiya reservoir to Tobruk
Phase VConnection of the eastern and western systems into a single network in Sirt
Sarir to Sirt800km
Tazerbo to Benghazi783km
Average water flow rate0.95m/s
Transit timeAround 9 days
Murzuk basin raw water soluble salt content300ppm
Kufra basin raw water soluble salt content250ppm
Phase I power demand65MW
Power linesSarir wellfield - 66kV transmission line; Tazerbo wellfield - 220kV national power line, transformed down to 66kV at substation
Project Timeline
Project initiated1983
Work commenced1984
Initial soil resistivity survey1989
First water receivedApril 1990
Phase I (Sarir to Benghazi) inauguratedAugust 1991
Cathodic protection system implemented1995
Phase II (Tripoli supply) completedSeptember 1996
Phase II Jeffara plain2000
Pumping station contract awardedOctober 2001
Pipe production plant O&M contract awarded2002
Phase III assignment periodJanuary 2002 to June 2005
Pumping station completion (expected)Summer 2004
Pumping station service and technical support contract initial term2004-05
Estimated time to final completion25 years
Cost
Phase I$14 billion
Pipe production plant O&M contract$350 million
Water pumping station turnkey construction$82 million
Phase III preliminary engineering / design$15.5 million
Total cost$27 billion (2004 estimate)
Key Players
OwnerGreat Man-made River Authority
FundingGovernment of Libya
Original project designBrown & Root / Price Brothers Cy
Main contractor - initial phasesDong Ah
Sub-contractorsEnka Construction & Industries; Thyssen Krupp Fördertechnik; Al Nahr Co.
Main contractor - phase IIINippon Koei and Halcrow
Pipe production plant operation and maintenanceSNC-Lavalin
ConcreteLibyan Cement
Pipeline coatingThane-Coat; Harkmel
Cathodic protection systemCorrintec
Pumping station construction / service and technical support contractFrankenthal KSB Fluid Systems Consortium


client logon
Home
Products & Services
Company A-Z
White Papers
Jobs & Careers
Press Releases
Advertise With Us
Events & Exhibitions
Newsletter
New On This Site
About Us
Atom FeedRSS Feed
What is RSS?