Greater Amman Water Supply Project, Jordan

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
National sustainable supply capacity
750 million m³/year
Current water demand (all uses)
>1 billion m³/year
Annual deficit
222 million m³ (1995); 251million m³ (2011 predicted)
Current annual allowance per capita
180m³ to 200m³
Amman water supply allocation (2003)
96 million m³/year
Total programme investment required to 2012
$5 billion
King Abdullah Canal / Zai WTP Project

On 9 March 2004, the European Union and the Kingdom of Jordan signed the agreement for a further €2 million of assistance to support the country's ongoing programme to improve water supply. This is the latest in a long line of contributions to a collaborative effort from a number of sources over the last ten years, including the World Bank, the US, Japan and Libya, together with some which came direct from individual EU Member States. The US Government alone has given $420 million in grant aid to the Jordanian water sector since 1993 and a total of some $630 million in grants and loans were secured from various sources for projects to be implemented during the five-year period from 1999 to 2004. Over 80% of this has provided critically needed water and wastewater infrastructure. The remainder has largely been used to support a number of important policy changes and finance capital investment, operation and maintenance.

This most recent EU funding is intended to help improve water management, reduce water losses and substantially upgrade the quality of water services in various parts of the Kingdom. A significant portion of this will be directed to the project instigated in 1996 to secure the water supply to the Greater Amman area.

The country's required water sector investment to 2012 is estimated at around $5 billion.

JORDAN WATER SUPPLY BACKGROUND

The scarcity of water in Jordan is widely seen as the single most important restriction on the country's sustainable economic growth, particularly given the increasing population, which was nearly 5.5 million in July 2003 and growing at a yearly rate of 2.78%. About 70% of the population is urban, with 2 million living within the Greater Amman area.

The country's annual water demand currently exceeds 1 billion m³ and is projected to rise to over 1.3 billion m³ by 2005, having nearly doubled since the mid-90s. Jordan's renewable water resources can supply around 750 million m³/year, leaving an annual deficit which has grown steadily, despite the huge programme of investment in the water sector, from 222 million m³ in 1995 to a predicted 251million m³ by 2011. The current annual allowance of 200m³ per capita lags significantly behind other countries in the region, being around 65% less than that available in Israel and Syria and 85% less than Egypt.

Long-term solutions are likely to involve the development of new water supplies, probably from outside its borders. Jordan already receives 60 million m³ from Israel and while it would be possible to extend the existing buy-in arrangements, this source can only be realistically anticipated to provide a relatively modest additional contribution in the future, perhaps up to a further 20 million m³.

Two major potential projects have been considered. The first involves importing water from Turkey; the second would require the construction of the "Red Sea-Dead Sea" canal, together with associated desalination facilities, and could increase water availability to both Jordan and Israel by as much as 850 million m³ annually. However, these would inevitably be huge undertakings, requiring enormous investment and many years to be realised.

To make the best use of investment in the interim, Jordan has developed a 14-year, $5 billion priority plan, aimed at alleviating the country's growing water crisis in the short to medium term. This employs two main approaches to narrow the gap between supply and demand - firstly, improving water supply management and secondly, increasing the efficiency of water use, thus making the most of the scarce resources available.

IMPROVING AMMAN'S WATER SUPPLY

Amman's distribution has long been dogged by problems and many residents receive a supply on just one day a week. Until very recently, over 50% of the water entering the city's distribution system was effectively unaccounted for, with half of this being lost by leakage and the rest due to poor administration, inadequate billing and lax payment collection. As a result of a series initiatives designed to address these problems, leakage has been reduced to roughly a third. In addition, the efficiency of customer charging within the Greater Amman water distribution system has improved significantly, now yielding a 25% profit over operational and maintenance costs. Education campaigns have also been supported, which have been very successful in boosting greater consumer awareness of the country's pressing water concerns.

Despite these improvements, providing the city with additional volumes of water remains a priority. One of the major measures envisaged to achieve this is the Disi-Mudawwara project, which aims to construct a pipeline from the Disi aquifer on Jordan's border with Saudi Arabia, to Amman, a distance of some 325km. This will provide the city with around 100 million m³/year of water at an estimated base capital cost of $600 million.

65 new boreholes will be created together with well field collectors, a 12,000m³ collector reservoir, a main pumping station and associated balancing tanks, a 16,600m³ regulating tank, a series of flow control stations, chlorination units and a terminal reservoir in Amman. Substantial operation and maintenance facilities will also be provided, including roadways, communication and telemetry services and electrical supply lines to the well field pumping stations.

The project's progress has not been straightforward. The aquifer holds fossil water and, since it receives no modern-day replenishment, is an unsustainable source which is already showing signs of depletion and increasing salinity from existing extraction. Its position on the Saudi border also makes the issue of further exploitation politically sensitive. A full feasibility study was completed in mid-1996, with preliminary design studies and geo-technical investigations completed the following year. Initial pre-qualifying bids on the Build-Own-Operate-Transfer contract were taken in late 2001 and final bids from two consortia were opened on 20 August, 2003 which are currently under evaluation by Jordan's Ministry of Water and Irrigation (MWI).

The project has a tentative five-year timetable and funding is another multi-donor effort. Libya will pay for around half the cost of the pipeline, sponsor equity accounts for 15% of total construction costs, the World Bank will support the project through partial risk guarantee and the balance comes from private investors and external funding agencies.

A number of other projects have already been implemented. Major repairs and redesigns, including upgrades to the existing 80mm to 1,200mm diameter primary pipelines, reservoirs and pumping stations have been undertaken across the Greater Amman network. The Japanese government funded a $70 million undertaking to increase the amount of water pumped to Amman through the King Abdullah Canal via the Balqa-based Zai water pumping station to 90 million m³/year.

In September 2003, the contract was awarded to construct the Zara-Maain water supply and treatment plant, which promises to provide the city with an extra 38 million m³/year - around 40% of Amman's annual allocation - by 2005. This $125 million project includes a pre-treatment system, desalination plant, a 40km water transmission pipeline and control systems.

KEY PLAYERS

Many parties have been involved in the various programme elements, including the Government of Jordan, the Jordan Valley Authority, Water Authority of Jordan, Ministry of Water and Irrigation and the Irrigation Advisory Service. Funding has come from the World Bank, the Arab Fund for Economic and Social Development, the United States Agency for International Development (USAID), the European Investment Bank, Kreditanstalt fuer Wiederaufbau, the European Union and a number of individual nations including Germany, Italy, Japan, Libya and the United Kingdom.

Major contractors include Lahmeyer International/Sigma JV, Hazen & Sayer, Morganti Group, Montgomery Watson, Suez-Lyonnaise des Eaux, Morganti Group/Ondeo Degremeont JV, Tokyo Sekkei Jimusho, Gibb, Camp, Dresser & McKee, Metcalf & Eddy, Harza, CH2MHill, ABT & Associates and Chemonics. Consultancy services were provided by DHV/SSI, Brown and Root North Africa, Consolidated Consultants, CEC/Sajdi & Partners and Dorsch Consult.

Lahmeyer International with worldwide experience partnered Sigma Consulting Engineers in supervising

Expand Image Expand Image
The King Abdullah Canal. A $70 million project increased the amount of water pumped to Amman along this the canal to 90 million m³/year.



Expand Image Expand Image
Jordan's position in the Middle East. The Kingdom is one of the most water-scarce countries in the world and its annual per capita water allowance lags significantly behind other countries in the region, especially its near neighbours Israel, Syria and Egypt.



Expand Image Expand Image
Multi-donor collaboration has funded a number of projects throughout Jordan, including new treatment plants and major repairs to the existing facilities and infrastructure.



Expand Image Expand Image
Sterilization ponds at As-Samra. The country's annual water demand currently exceeds 1 billion m³ and is projected to rise to over 1.3 billion m³ by 2005.



Expand Image Expand Image
Amman has particular water supply problems. A third of the Kingdom's total inhabitants live within the Greater Amman area.



Expand Image Expand Image
A public awareness walk at Amman's Water Use Conservation Festival. A long-term programme of such events has made a significant contribution to reducing water wastage in the city.



Expand Image Expand Image
Diagram of land usage in Jordan. The country's total area is 92,300km², of which all but 329km² is dry land; only some 750km² is irrigated.



Expand Image Expand Image
The route of the proposed Red Sea-Dead Sea canal. The planned 180km conduit, consisting of tunnel and canal sections, would carry1.8 billion m³/year of seawater to associated power / RO desalination projects and provide 850 million m³/year of fresh water to Jordan, Israel and Palestine.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the water and wastewater industry