Al Hidd Desalination Plant, Bahrain

Email-Icon
 
Print-Icon
 
Link-to-us
key facts
Key Data
Order Year
1997
Plant Type
Desalination Plant
Location
Hidd, Bahrain
Estimated Investment
$90 million
Completion
2000
Sponsor
Government of Bahrain (Ministry of Electricity and Water)
Lead Contractor
Black and Veatch

The Government of Bahrain has instigated a $360 million project, involving the construction of the Al Hidd power and desalination facility on Muharraq Island. The project was undertaken by an international consortium, led by Black and Veatch, a US engineering and construction company. The first phase was to increase the power capacity of the island's new gas fired power plant to 260MW.

Demand for both power and water in Bahrain has been approaching production capacity recently, with demand outstripping supply at a rate which would create major problems in the future if the government did not intervene. The construction of the Al Hidd plant is the first stage in trying to ease these pressures.

A report for the Electricity and Water Ministry was prepared by British consultants Mott Macdonald, and concluded that Bahrain will need an increased 400,000 cubic metres per day of potable water by the year 2005. The report recommended the construction of the three new water desalination stations, each with a capacity of 135,000 cubic metres per day, stating that Bahrain's ground water supply would run dry in four years if measures were not taken.

The island's former desalination capacity was 203,400 cubic metres per day, but the old plant treated brackish groundwater rather than the seawater which is being used to replace the diminishing water of the aquifer.

Consumption reached 101 million gallons per day in 1998, and is expected to hit 126 million gallons per day in 2005. Such levels, outstripping the capacity of the three previous plants, meant that water was being drawn from a threatened aquifer already brackish due to seawater infiltration. Seawater has in turn been increasing salt parts per million in the ground water.

AL HIDD PROJECT MAKE-UP

The international consortium was composed of Black & Veatch (B&V), ABB of Sweden/Switzerland and Japan-based Hitachi Zosen Corporation. B&V was responsible for the provision of plant engineering and the supply of associated equipment. ABB supplied the turbine unit and Hitachi Zosen provided the desalination plant. The first phase of the combined facility began early in 1997, and was completed in mid-1999. The desalination plant treats seawater through a multistage flash process, and produces 30 million gallons per day.

DISTILLATE FORWARDING AND PUMPING

The project contract required the construction of the Hidd distillate forwarding station, which comprises a 410 million litres distillate water storage in 45 million litres steel tanks. A 135 million litres/day forwarding pumping station was built, which sends flows to Hidd BS, Muharraq BS, Hoora BS, Sanabis BS and Seef BS and which has an option for gravity supply for low flows.

BLENDING STATIONS

A Seef blending station was built, which constitutes a nine million litres distillate water storage in 4.5 million litres steel tanks, a 4.5 million litres ground water storage in 4.5 million litres steel tanks, and a 22 million litres distillate water storage in 22.7 million litres steel tanks. Furthermore, blending pumps and pumps which forward to Janusan, Budiya and Saar were installed.

In addition to this, a blending station was built in West Rifa which includes an 18 million litres distillate water storage in 9 million litres steel tanks, an 18 million litres ground water storage in 9 million litres steel tanks, a 114 million litres distillate water storage in 23 million litres steel tanks, as well as blending and forwarding pumps.

Finally, the project required the installation of a 45km twin and single ductile iron transmission mains, as well as refurbishment of the existing blending stations to increase the capacities of existing facilities.

The desalination plant at Bahrain was part of the Bahraini Governmnet's $360 million project, which

Expand Image Expand Image
The desalination plant at Bahrain was part of the Bahraini Governmnet's $360 million project, which involves the construction of a power and desalination facility on the Muharraq Island.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Press Releases
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the water and wastewater industry