Key Data:
Project elements
Upgrading water supply schemes in 13 District Centres; sanitation and health education; works supervision and technical assistance
Project cost
$17.5 million
Supply target
27 litres / person / day
Project Timeline:
Initial national water services review
1993
National master plan formulated
1994
Phase III commenced
March 2000
Phase III construction completed
2003
ADB funding concluded
December 2003
Phase III overall completion expected
Mid-2004
Conclusion of master plan provisions
2010
Key Players:
Financing
African Development Bank (84%), Government of Malawi (16%)
Executing agency
Ministry of Water Development
Consulting engineers
Chapita
Project accountant
Elizabeth Gondwe Associates
Distribution and delivery
Regional water boards
Local operation / administration
Water point committees