Key Data:
Current
140 million US gallons/day (530,000m³/day)
Final
215mgd (815,000m³/day)
Service area
92,124 acres (36,850 hectares)
Population served
500,000 (northern section of the city)
Treatment type
Coagulation, flocculation/sedimentation, filtration and disinfection
Volume (at maximum operating level)
1,807 million gallons (6.8 million m3)
Project cost
$32m (early start improvements)
Project Timeline:
Phase I construction began
Summer 1998
Construction completed
Winter 2003
Phase II construction began
September 2002
Final completion
February 2005
Construction began
August 2003
Anticipated completion
August 2007
Scheduled to begin
January 2007
Anticipated completion
November 2009
Scheduled to begin
November 2007
Anticipated completion
November 2009
Scheduled to begin
November 2009
Anticipated completion
November 2010
Total project scheduled completion
2012
Key Players:
Plant owner/project sponsor
City of San Diego Water Department
Early start contractor
Archer Western