Key Data:
Design Engineers
JV Parsons Engineering Science Inc; Harza Engineering Co.
Excavation Engineers
Ladd Associates
Main Contractor
Kiewit Pacific
Reservoir Capacity
7.8 billion gallons
Construction Method
Roller-compacted concrete
Roller-compacted concrete
1.3 million cubic yards
Project Timeline:
Phase One:
Olivenhain Dam
Olivenhain Pipelines & Interconnections
Olivenhain Pump Station
San Vicente/Moreno-Lakeside Interconnect Pipeline
1998 – 2003
Phase Two:
San Vicente Pump Station
San Vicente to Second Aqueduct Pipeline and Interconnection
Operations Center Upgrade
2002 – 2006
Phase Three:
Lake Hodges Inlet/Outlet
Lake Hodges Pipeline
Lake Hodges Pump Station
Pipeline 3 Pump Station and Interconnection
Pipeline 4 Pump Station
2004 – 2008
Phase Four:
San Vicente Recreational Facilities
San Vicente Dam Raise
2008 - 2010