Peacehaven Wastewater Treatment Works, United Kingdom

Email-Icon
 
Print-Icon
 
Link-to-us
 
Related Projects
key facts
Key Data
Project Type
Wastewater treatment plant
Location
Peacehaven, East Sussex, UK
Plant Capacity
95ML of wastewater per day
Total Project Cost
£300m
Project Proposed
1997
Approval Received
August 2008
Planning Permission Received
October 2008

Peacehaven Wastewater Treatment Works is an environmental improvement scheme at Lower Hoddern Farm in Peacehaven, East Sussex, UK. The project will treat 95 million litres (ML) of wastewater a day.

The £300m facility has been proposed by Southern Water, the utility provider for water supply and wastewater treatment services in south-eastern UK. The plant will treat wastewater generated from Brighton and Hove, Rottingdean, Saltdean, Telscombe, Woodingdean and Peacehaven.

Work on the project began in July 2009. The plant is scheduled to be completed and fully operational by spring 2013.

Purpose of project

Southern Water has worked on several multi-million-pound wastewater schemes across the south-east. Wastewater from homes in Peacehaven and Brighton and Hove, water from factories and rainwater are treated at Portobello wastewater treatment works at Telscombe Cliffs, East Sussex. Wastewater at Portobello undergoes basic treatment after grid removal. It is pumped to the sea through a 1.8km outfall pipe. The Peacehaven project will ensure a cleaner discharge into the sea.

Background

"Two new underground pumping stations will be constructed to pump wastewater to the new plant."

In 1997 a proposal for a new plant at Portobello by Southern Water was refused by East Sussex County Council. Southern Water considered an alternative site. A total of 66 potential locations were identified and reviewed by the company and a local authority consultative group.

Peacehaven was selected and planning applications for the facility and infrastructure were submitted in April 2005. The proposed plant will cross administrative boundaries and serve the Brighton and Hove catchment area, along with Ovingdean, Telscombe Cliffs, Woodingdean, Roedean, Saltdean, Rottingdean and Peacehaven.

In July 2007 the plan was rejected by the government after a public inquiry. A new design with new features and landscaping was proposed. It was approved by East Sussex County Council in August 2008. Planning permission for the works was granted by the council after consultation with the secretary of state in October 2008.

Construction

The project involves the construction of a new wastewater treatment plant, a sludge recycling centre and an 11km underground pipeline for transferring sewer water to the Peacehaven facility. A 2.5km outfall pipeline will discharge treated water into the sea.

The sewer pipe tunnel will range from depths of 8m to 40m and will be dug by two tunnel boring machines (TBMs). The 2.4m-diameter TBMs have rotational cutting wheels at the front, which minimises disturbance above the ground. To connect local sewers along the route, shafts will be built. They will be covered by manholes. Pipejacking will also be used for some sections.

Two new underground pumping stations will be constructed to pump wastewater to the plant. The Portobello plant will be used as a pumping station and will be covered with a grassed roof. Another pumping station, to be constructed at Marine Drive, will be enclosed in a domed structure to allow it to integrate with the landscape. Most construction work is expected to be complete by the end of 2011.

Technology

The Peacehaven plant will have a pre-treatment facility that will remove oil, fat, grease and grit from wastewater.

"The plant will have a pre-treatment facility that will remove oil, fat, grease and grit."

The facility will have Multifloä lamella clarifiers for primary treatment and Biostyrä biological aerated flooded filters (BAFF) for secondary treatment. The technology will be installed at the plant from 2010 to 2013.

Treated water will be released 2.5km offshore at Friars Bay, meeting regulations on chemical oxygen demand and biochemical oxygen demand. Sludge will be treated to generate agricultural fertiliser.

Key players

Southern Water has contracted 4Delivery (4D), a consortium of United Utilities, Costain and Montgomery Watson Harza (MWH), for the project's implementation. In June 2009 a £225m construction contract was awarded to 4Delivery. 4D will operate and maintain the plant for two years after the project's completion.

In November 2009 the consortium awarded a £10m contract to Veolia Water Solutions and Technologies to provide clarifiers and BAFF technology for the plant.

Opposition

Peacehaven is an area of natural beauty. A group, Peacehaven Residents Opposed to Urban Development (Proud), opposed the works.

Environmental impact

Southern Water has conducted environmental studies regarding the protection of reptiles, rabbits and foxes in the construction area. The plant is designed to blend in with the landscape.



Expand Image Expand Image
The project will treat 95 million litres (ML) of wastewater a day.



Expand Image Expand Image
Peacehaven Wastewater Treatment Works is an environmental improvement scheme at Lower Hoddern Farm in Peacehaven, East Sussex, UK.



Expand Image Expand Image
Sludge will be treated to generate agricultural fertiliser.



Expand Image Expand Image
Southern Water has conducted environmental studies regarding the protection of reptiles, rabbits and foxes in the construction area.



Expand Image Expand Image
The plant has been designed to blend in with the landscape.



Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Newsletter Sign-Up
For all the latest news in the industry, sign up here

Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Industry News
Gallery
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the water and wastewater industry