Key Data:
Volume of wastewater treated
19.7 million m³/y
Activated sludge tank capacity
7,000m³ each
Secondary clarifiers
4 x 48m diameter
Secondary treatment BOD removal
75% to 80%
Secondary effluent BOD load
0.5t/d
Polishing lakes detention period
Up to 35 days
New faecal Coliform standard
1,000cfu per 100ml (median value)
Final UV treatment system (after expansion)
Six-channel system (1,296 lamps)
UV treatment full peak flow
3m³/s to 4m³/s
UV treatment system cost
NZ$2.26 million
Total estimated cost (Stage 4)
NZ$31 million
Estimated cost of the new outfall
NZ$60 million
Project Timeline:
Resource consent approval
April 2001
Stage 4 upgrade duration
3 years (2002-05)
New faecal Coliform standard effective from
1 January 2004
Foreshore sewer upgrade Phase I completed
November 2003
Foreshore sewer upgrade Phase II commenced
May 2004
Deadline for reuse/composting of biosolids
2007
New sea outfall completion required by
1 July 2008
Key Players:
Project sponsor / finance
North Shore City Council
Regulatory body
Auckland Regional Council
Consulting engineers
Sinclair Knight Merz
Environmental planning consultants
Simpson Grierson
Nutrient removal system design
URS
Maintenance contractor
Techscape