Sulaibiya Wastewater Treatment and Reclamation Plant, Kuwait

 

Key Data:

Plant type
Reverse osmosis (RO) and ultra-filtration (UF) membrane-based water purification of wastewater
Plant output
Potable quality water for non-potable uses in agriculture, industry and aquifer recharge
Input feed
375,000m³/day
Output product
311,250m³/day
Waste
63,750m³/day
Water recovery efficiency
85% (RO phase), 83% (overall)
Future expansion design potential
600,000m³/day (input feed)
Raw Wastewater Input Characteristics
Temperature
15°C to 36°C
TSS
300mg/l
TDS
1,280mg/l
BOD5
400mg/l
COD
700mg/l
Sulphates
300mg/l
H2S
66mg/l
Total N
70mg/l
Total P
15mg/l
Oil and grease
40mg/l
Product Water Characteristics (Monthly Average Value)
pH
6-9
TDS
<100mg/l
TSS
<1mg/l
BOD5
<1mg/l
NH4-N
<1mg/l
NO3-N
<1mg/l
PO4
<2mg/l
Oil and grease
<0.05mg/l
TOC
<2mg/l
Hardness as (Ca CO3)
<10mg/l
Enteric viruses
5 MPNIU/10 l
Total coliform
<2.2 colonies/100ml

Plant Details:

Disc filter elements
5 disc filters (60µm)
Ultra-filtration (UF) elements
Total membrane area 304,640m²; 68 skids with 32 pressure vessels; pore size 30nm
UF performance
Total removal of SS; log 5 removal of bacteria; log 4 removal of viruses
Reverse osmosis (RO) elements
24 first array skids;12 second array skids; six third array skids; each skid comprises 72 pressure vessels containing seven membrane modules apiece; 48 associated pumps
Diffuser array
50,000 Sanitaire Silver Series Diffusers; 2,600 Sanitaire Coarse Bubble Diffusers
Aeration, pumping and mixing system components
13 Blowers; 45 Mixers; 72 Flow boosters; 27 Recirculation pumps; >25km of air main and flooring pipes
Digester volumetric load
2.45kg/VS/m³/d
Contract type
BOT
Concession period
30 years (30 months D&B, 27.5 years O&M)
Total project cost
KD130 million ($430 million)
Loan value
$377 million
Loan period
25 years
Debt-equity
85:15
Projected revenue
>$2 billion
Winning water tariff
$0.47/m³

Project Timeline:

Tender pre-qualifications
October 1998
Tender bids submitted
April 2000
BOT contract awarded
May 2001
Financial close / service contracts signed
June 2002
Construction begun
July 2002
Aeration / pumping / mixing contract awarded
January 2003
Dynamic hydraulic analysis
March 2003 - February 2004
Pipework contracts awarded
May 2003
Construction completed
November 2004
Formal dedication ceremony
16 March 2005
First water supplied
December 2005

Key Players:

Contract administration
Kuwaiti Ministry of Public Works
Main contractors
Kharafi, Ionics, Bechtel and United Utilities
Utilities Development Company (UDC)
Kharafi Group (75%) and Ionics (25%)
Financial adviser to UDC
ABN Amro
Technical advisers and construction managers
Camp Dresser & McKee; KEO International Consultants
International legal counsel
Allen & Overy
Insurance advisers
Arab Commercial Enterprises
Finance arrangers
National Bank of Kuwait; Gulf Bank; The Bank of Kuwait and the Middle East
Facility agent
National Bank of Kuwait
Arrangers legal counsel
Shearman & Sterling; Al-Essa, Al-Bader & Partners
Insurance advisers
Willis
Financial model auditor
PKF
Design review / technical due diligence
Halcrow
Construction
Kharafi and Philipp Holzmann JVC
Plant design
ILF
RO/UF membrane treatment systems
Ionics Italba
XIGA ultra-filtration membrane technology
NORIT
Aeration, pumping and mixing system
ITT Industries
Piping and internal cement / epoxy
Xinxing Ductile Iron Pipes
Pipe couplings
Viking Johnson
Dynamic hydraulic analysis
WL Delft Hydraulics
Plant operation and maintenance
Kharifi, Ionics and United Utilities
Membrane system operation and maintenance
Ionics


Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Press Releases
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the water and wastewater industry