Key Data:
Proposed Flows and Discharge
Project Timeline:
Thames Tideway Strategic Study formed
2000
Final Report
February 2005
Supplementary Report Delivered
November 2005
Option Assessment Report to Defra
December 2006
Governmental Approval on the Tideway Tunnel
March 2007
Crossness Improvement Work
Spring 2008 – 2014
Mogden Improvement Work
Spring 2008 – Spring 2012
Tideway Tunnel Construction Schedule
2012 – 2020
Cost:
Tideway Tunnel
£2bn – 2.5bn (estimated)
Key Players:
TTSS Members
Thames Water, Defra, the EA, GLA and Ofwat
Ofwat Consultants
Jacobs Babtie
Primary Sludge Settlement Equipment
Hydro International
Tideway Tunnel:
Length
32.2km (Hammersmith to Beckton); 5.5km (Abbey Mills to Beckton)
Total Storage Volume
1,638,000m³