Key Data:
Source Water
Secondary-level wastewater
Pre-Treatment
Flocculation (Bundamba and Luggage Point); high-rate clarification (Gibson Island)
Micro-Filtration Pore Size
0.1µ - 0.2µ
Gibson Island AWTP
50mld in October 2008; additional 50mld after December 2008
Project Timeline:
Construction Began
March 2007
Stage 1A Completed
August 2007
Bundamba AWTP Practical Completion and Hand Over
July 2008
Stage 2 to be Completed
October 2008
Project Completed
December 2008
Key Players:
Project Sponsor
Western Corridor Recycled Water Pty Ltd
Government Partners
The Department of Infrastructure and Planning, National Water Initiative, Brisbane City Council and Ipswich City Council
Bundamba AWTP
Thiess and Black & Veatch
Gibson Island AWTP
MWH, Worley Parsons, Baulderstone Hornibrook and United Group Infrastructure
Luggage Point AWTP
CH2M Hill, Laing O’Rourke with assistance from Connell Wagner and Hatch
Eastern Pipeline
AJ Lucas, Transfield Services, GHD and Sunwater
The Western Pipeline
McConnell Dowell, Abigroup and GHD
Project Assets and Infrastructure Development; Subsequent Plant / Pipeline Operation
Veolia Water Australia