Shatin Sewage Treatment Works Expansion

Track this project

Receive an alert email whenever we update this page.

Start tracking

I consent to Verdict Media Limited collecting my details provided via this form in accordance with our Privacy Policy

You are in control of the communications you receive from us and you can update your preferences anytime to make sure you are receiving information that matters to you. Please check our privacy policy to see how we protect and manage your submitted data.

Population Equivalent (0.06kg / day)

950,000

Peak Flow

1,020 Mld / day

Stage I and II Aeration Tank Retention Time

Eight hours

1991 Revised Aeration Tank Retention Time

11 hours

Stage I and II Capacity

205,000 cubic metres / day

1991 Revised Capacity

150,000 cubic metres / day

Current Capacity

340,000 cubic metres / day

Typical wastewater loadings

BOD<span class="sup">5</span>

57,000 kg / day

TSS

67,000 kg / day

TKN

15,700 kg / day

Chloride ions

2,000 to 7,000mg / l

Wastewater temperature

15 to 32&#176;C

Final effluent quality

BOD<span class="sup">5</span>

20 mg / l (at 95 percentile) 40 mg / l (max)

TSS

30 mg / l (at 95 percentile) 60 mg / l (max)

Total Nitrogen

20 mg / l (annual average) 35 mg / l (max)

NH<span class="sup">3</span>-N

5 mg / l (annual average) 10 mg / l (max)

UV project cost

&#36;124 m HKD ($16 m)

Expansion project cost

&#36;2,425 m ($312 m)

Plant Owner

Hong Kong Drainage Services Dept

UV Disinfection Contractor

Jardine Engineering

Other Contractors

Biwater, Leader Civil Engineering, Sun Fook Kong, Hydrotech Professional, Hang Kee Construction &amp; Engineering, ATAL Engineering Ltd and China Railway Engineering Corporation

Stage I commissioned

1982

Stage II commissioned

1986

Stage III expansion began

April 2001

Stage III completion

September 2004

UV project completed

December 2009

Expansion project completion

August 2010