Seine Aval WWTP Upgrade, Achères, Paris , France

 
 
key facts
Key Data
Treatment capacity
2.1 million m3/day
Facility sizing
Dry weather
24m3/sec
Wet weather
45m3/sec
Exceptional peak
52m3/sec
Nitrification basins
84 x 173m2
Denitrification basins
11 x 147m2

Part of a 15-year scheme launched in 2000 to improve wastewater treatment for the whole of the Greater Paris area, the upgrade at Seine Aval – Europe’s largest WWTP – is a major programme of works. It includes an extensive new nitrification/denitrification facility.

Scheduled to enter service in 2007, it forms the main element in the planned extension of full nitrogen treatment to all of the region’s wastewater by 2015. The scheme has been designed to meet the demands of both projected population growth and new discharge regulations.

The project also includes significant expansion of the existing sludge processing arrangements and the installation of five HVA substations, together with extensive associated equipment and instrumentation.

Environmental considerations have been at the core of this project from the outset, not simply as a result of its primary goal to reduce pollution into the Seine, but also in terms of working practice, material selection and the mitigation of its impact on the immediate area. In addition, a 45 hectare meadow has been created, some 85 hectares of parkland will ultimately be established along the river and more than 25,000 trees will be planted.

Syndicat Interdépartemental pour l’Assainissement de l’Agglomeration Parisienne (SIAAP) – the wastewater authority for the region – awarded the contract to a consortium led by OTV France. The group comprises two sub-consortia from the fields of civil engineering and wastewater treatment.

The total project cost approaches €391 million.

BACKGROUND

Originally commissioned in 1940, the Seine Aval plant at Achères treats the effluent from around 80% of the population of the Parisian region and has a rated capacity slightly in excess of 2 million m³/day.

The existing biological treatment train consisted of an activated sludge process for organic carbon removal, but changes in the regulations regarding the nitrogenous component of effluent led to a four-year, on-site pilot study of three nitrification prototype reactors. As a result, the decision was made to use the Biostyr process, the new facility requiring the construction of 84 nitrification and 11 denitrification basins and the installation of some 55,000m³ of filter medium.

In addition, the wider improvement project will implement new regional treatment systems, enabling the volume of effluent arriving at the plant to reduce – to 1.7 million m³/day by 2007 when the new nitrogen treatment has been commissioned and to1.5 million m³/day by 2015. The scheme’s slogan – traitez moins, traitez mieux (treat less, treat better) – perfectly sums up its goal.

TREATMENT REGIME

The arriving flow undergoes substantially conventional initial phases, with a pre-treatment stage comprising screening, de-gritting and de-oiling. It is followed by primary settlement to remove suspended solids before entering the activated sludge process.

Effluent clarification uses a ballasted coagulation/flocculation process with lamella settling. This system, which was selected for its high efficiency and turbidity removal, was commissioned in 2004 and is designed to exclude phosphorus in normal conditions and treat storm flows in wet weather. The system is a compact process using microsand to provide a high surface area to enhance flocculation, assist floc formation and act as ballast which aids rapid settlement.

Once completed, the new Biostyr installation will form the last step in the treatment train and will achieve full nitrification of the flow and remove any residual carbon or suspended solids. The effluent leaving the process will then be subject to partial denitrification to 30%.

The Biostyr process combines total nitrogen removal with treated water clarification in a single stage and within a single vessel, the light polystyrene bead media floating when immersed and the water being treated filtering upwards through it. This arrangement enables the accumulated solids to be removed by periodic gravity backwashes using treated water, thus avoiding the need for extra pumps and reducing energy costs.

In addition, the use of a counter current backwash reduces potential odour nuisance, since both the air and the nozzles on the effluent side are only ever in contact with treated water.

The new facilities have been sized to cope with flows ranging from a dry weather 24m³/sec to 45m³/sec in the wet, with the capability of handling exceptional peaks of up to 52m³/sec.

Residual sludge from the process will be dewatered firstly by flotation to 4% dryness and subsequently to 6% by centrifugation.

In addition, the plant’s overall sludge regime is also undergoing a major upgrade to extend the pre-existing on-site treatment of its carbon and phosphorus content to encompass thickening, digestion, thermal treatment and dewatering before the final product is landfilled.



Expand Image Expand Image
The upgrade at Seine Aval is a major element in the 15-year scheme to improve wastewater treatment for the whole of the Greater Paris area.



Expand Image Expand Image
Schematic of the Biostyr process. Central to the plant’s new nitrification/denitrification facility, the light polystyrene bead media – biostyrene – encourages the formation of a surface biofilm with an inner anoxic zone and an outer aerobic zone.



Expand Image Expand Image
The upgrade programme also includes a major expansion of the existing sludge processing arrangements and the installation of new electrical substations.



Expand Image Expand Image
Schematic of a Biostyr module: the process combines both total nitrogen removal and clarification in a single stage within the same bioreactor. The system’s counter current backwash also offers energy savings and significantly reduces odour nuisance.



Expand Image Expand Image
Scheduled to enter service in 2007, the new nitrification/denitrification plant is intended to help with the goal of full nitrogen treatment for all of the region’s wastewater by 2015.



Expand Image Expand Image
Earlier efforts to reduce pollution into the Seine have already begun to bear fruit. A recent study identified 35 species of fish within the boundaries of the city – compared with 15 only two years previously.


Post to:
Delicious  
Digg  
reddit  
Facebook  
StumbleUpon  


Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Features
White Papers
Jobs & Careers
Press Releases
Events & Exhibitions
Newsletter
Advertise With Us
About Us
Client Area

The website for the water and wastewater industry