Southern Delivery System Water Project, United States of America
Key Data
The Southern Delivery System (SDS) project is the largest of its kind to be undertaken in Colorado, US. The project will carry Arkansas River water from the Pueblo Reservoir to the cities of Colorado Springs and Fountain, as well as to the Pueblo West and Security Water districts. It will have an ultimate capacity of 96 million gallons a day (MGD).
The project is being executed by Colorado Springs Utilities in two phases at a total cost of $1.45bn. Construction of the $880m phase I part of the project commenced in June 2011 and is scheduled to commence operations in April 2016.
About 300 construction jobs are expected to be generated each year by the project.
Purpose of the SDS project
The SDS project is being undertaken to provide a safe, economical and reliable water supply to the Colorado Springs and nearby communities. These regions are not located near a river system and hence rely on pipeline delivery to meet their water needs.
Population in these regions is expected to grow in the range of 1.2%-3.7% between 2000 and 2030. The existing water supply infrastructure is aging and requires major upgrades to sustain the future demand arising from this population growth.
The SDS project was considered as the best solution among the several alternatives considered to addressing these problems.
The project has been in the making for the past 20 years. It was originally proposed in the 1980s with planning commencing in the 1990s. The system will meet the needs of the region through 2046 and beyond.
Facilities
The main components of phase I of the SDS include modifications to the North Outlet Works of the Pueblo Dam, 62 miles (100km) of the underground raw and treated water pipeline, along with a 500MGD water treatment plant.
Three pump stations at Juniper near the Pueblo Dam and at Bradley and Williams Creek in El Paso County will also be built as part of phase I.
Water will be stored in the Pueblo Reservoir and delivered to the regions through the pipeline.
Phase II of the project includes construction of a storage reservoir at Upper Williams Creek and an exchange reservoir at Lower Williams Creek.
A water treatment plant expandable up to 100MGD and pump stations are also part of this phase. Works on these components will be undertaken between 2020 and 2025. depending upon the demand.
The Upper Williams Creek reservoir will have a storage capacity of 30,500 acre-feet (ten billion gallons). It will enable water to be stored during low demand periods and used during periods of high demand.
Construction of the Southern Delivery System
Construction works commenced with modifications to the North Outlet Works of the Pueblo Dam. The modifications will enable water to be drawn from the Pueblo reservoir and delivered to the Juniper pump station through the underground pipeline. Concrete pouring at the North Outlet Works commenced in July 2011.
Construction of the underground pipeline has been divided into several sections. These sections, including Pueblo Dam Connection, Finished Water Pipeline, North Pipeline and South Pipeline, have been further segmented into various work packages.
The Pueblo Dam Connection has been divided into two work packages. Finished Water Pipeline, North Pipeline and South Pipeline have been divided into four work packages each.
As of August 2011, 1,800 cubic yards of concrete was poured for creating the foundations of the Pueblo Dam Connection. Excavation works for the construction of the Southern Pipeline are currently underway.
Key players taking part in the project
ASI Constructors was appointed as the primary contractor for the North Outlet Works. Subcontractors include High Country Pipeline, Springs Fabrication, Transit Mix and Rocky Mountain Crane Service.
Other contractors include Reynolds, Garney Construction and HCP Constructors.
CH2M HILL is providing project management and design services for the SDS.
McCarthy Building Companies and Carollo Engineers will build the 500MGD water treatment plant.
Preliminary design of the Finished Water Pipeline was carried out by Dewberry-Integra.